DESIGN OF A PLANT FOR THE PRODUCTION OF 750,000 STANDARD M3/DAY OF HYDROGEN BY PARTIAL OXIDATION OF HEAVY OIL FEEDSTOCK
ABSTRACT
The design of a plant producing hydrogen by partial oxidation of oil feedstock has been carried out. Purity of hydrogen obtained from the process was set at 98%, with minimal levels of impurities. The main process involved include the partial oxidation of the heavy fuel oil feedstock in a flame lined reactor called a gasifier to produce hydrogen. The successive units in the plants are purification units to ensure that the product specification of 98% purity of hydrogen is met. A water gas shift converter was also present to improve hydrogen yield. Waste heat energy generated from the gasification process is used in the waste heat boiler to generate steam for the plant. These purification units include: Quencher, Initial H2S scrubber, final H2S removal, CO2absorption.
The chemical and mechanical design of the main equipments in the plants was carried out and the results presented. Costing and HAZOP analysis of each item of equipment is also provided. Detailed economic and profitability analysis was done and general safety and environmental issues were addressed.
TABLE OF CONTENTS
CONTENTS PAGE
1.1 HYDROGEN GAS: BRIEF HISTORY AND MARKET VALUE
1.3 LIMITATIONS OF HYDROGEN PRODUCTION
2.1.3 ENTRAINED FLOW GASIFIERS
2.2.1 TYPES OF WASTE HEAT BOILERS
2.2.2 WASTE HEAT BOILER DESIGN CONSIDERATIONS
2.3.1 HORIZONTAL DESIGN: CFQ QUENCHER
2.3.2 VERTICAL DESIGN: CCQ-QUENCHER
2.4 SCRUBBING SYSTEMS (INITIAL H2S REMOVAL)
2.5.1 DESIGN AND OPERATION OF WATER GAS SHIFT REACTORS
2.7 FINAL H2S REMOVAL (CHEMOSORPTION)
2.7.1 PRESSURE SWING ABSORBER DESIGN
2.8.3 HOT POTASSIUM CARBONATE (BENFIELD) FOR CO2 REMOVAL
2.9.3 AIR-COOLED EXCHANGERS 43
2.9.5 PLATE HEAT EXCHANGERS 45
2.9.6 SHELL AND TUBE HEAT EXCHANGERS 47
2.9.7 MEAN TEMPERATURE DIFFERENCE ( DRIVING FORCE) 48
3.2 ENERGY BALANCE AROUND CO CONVERSION STAGE
3.3 ENERGY BALANCE AROUND THE GASIFIER 58
CHAPTER FOUR 61
4 CHEMICAL ENGINEERING DESIGN 61
4.1 TANK ONE (FEED STORAGE TANK FARMS) 61
4.2 TANK 2 (FRESH FEED SURGE DRUM) 62
4.3 TANK 3 (STORAGE TANK FARM) 62
4.4 THE HEAVY FUEL OIL GASIFIER 64
4.6.5 HEIGHT OF THE COLUMN: Z 76
4.8 CARBON MONOXIDE CONVERSION UNIT 79
4.8.1 REACTOR TYPE: FIXED BED REACTOR 80
4.8.2 CATALYST: CHROMIUM – PROMOTED IRON OXIDE 81
4.8.3 CATALYTIC CONVERTER SIZING 84
4.9 FINAL H2S REMOVAL STAGE 85
4.9.2 REGENERATION OPERATION 86
4.10 CARBON DIOXIDE REMOVAL 92
4.10.1PACKING MATERIAL: PALL RINGS (PLASTIC) 94
4.11.3 VISCOSITY CORRECTION FACTOR 97
4.11.4 OXYGEN STREAM PRE-HEATER. 98
4.11.5 AIR-COOLED EXCHANGERS 102
4.12.1APPROXIMATE PUMP-SIZING CALCULATION PROCEDURE 109
4.12.2THE METERING RAM PUMP 111
5.1.3 MATERIAL OF CONSTRUCTION 115
5.1.4 THICKNESS OF THE REFRACTORY BRICK 116
5.1.5 MINIMUM WALL THICKNESS 116
5.1.6 MINIMUM HEAD THICKNESS 117
5.3.1 MATERIALS FOR CONSTRUCTION 118
5.4 THE INITIAL H2S ABSORBER 121
5.4.2 SUPPORT FOR ABSORBER 124
5.5.1 OPERATING AND DESIGN TEMPERATURES AND PRESSURES 125
5.5.2 VESSEL DIMENSIONS AND ORIENTATION 125
5.5.3 CONSTRUCTION MATERIALS 126
5.5.6 HEATING AND COOLING JACKETS OR COILS 127
5.5.7 INTERNAL FITTINGS SPECIFICATION 127
5.6 THE FINAL H2S ABSORBER 128
5.7.2 AXIAL STRESS DUE TO PRESSURE 130
5.7.3 STRESS DUE TO DEAD LOAD 130
5.7.4 EFFECT OF ATTACHMENTS 132
5.7.5 SUPPORT FOR ABSORBER 133
6 PLANT HAZARD AND OPERABILITY STUDY 138
6.8.4 SATURATOR – DESATURATOR 152
6.8.5 THE FINAL H2S ABSORBER 153
7.1 ECONOMIC AND PROFITABILITY ANALYSIS: GASIFIER 158
7.2 ECONOMIC AND PROFITABILITY ANALYSIS: QUENCHER 161
7.3 COSTING (CO CONVERSION) 163
7.4 COST AND FEASIBILITY ANALYSIS (FINAL H2S REMOVAL) 164
7.5 COSTING AND PROFITABILITY (CO2 REMOVAL) 166
7.6 ESTIMATION OF COST (1ST HEAT EXCHANGER) 168
7.7 ESTIMATION OF COST (2ND HEAT EXCHANGER) 169
CHAPTER EIGHT 170
8 CONCLUSION AND RECOMMENDATION 170
8.1 CONCLUSION 170
8.2 RECOMMENDATION 171
REFERENCES 172
A.1 SIMULATION 175
A.2 PLANT AND SITE LAYOUT 176
A.3 PROCESS INFORMATION 177
A.4 CALCULATIONS 178
LIST OF TABLES
TABLE | TITLE | PAGE |
2.1 | Classification of Gasifiers | 10 |
2.2 | Comparison of Calculated and Experimental Solubility Data for Scrubbing Solvents | 23 |
3.1 | Composition before H2S Removal | 51 |
3.2 | Composition after H2S Removal | 51 |
3.3 | Composition Out of WGS Reactor | 53 |
3.4 | Final H2S Remover Outlet | 54 |
3.5 | Percentage Composition of Constituents from Final H2S Removal Outlet | 54 |
3.6 | Composition of the Inlet into the CO Conversion Stage | 57 |
3.7 | Composition of the Outlet from the CO Conversion Stage | 57 |
3.8 | Energy Balance of Outlet Stream from Gasifier | 59 |
3.9 | Energy Balance of Inlet Stream to Gasifier | 60 |
4.1 | Tank 1 Dimensions | 61 |
4.2 | Tank 2 Dimensions | 62 |
4.3 | Tankage Dimensions | 63 |
4.4 | Rate Constant Values At Specific Temperatures | 66 |
4.5 | Equilibrium Constants at Specific Temperatures | 66 |
4.6 | Composition of Crude Gas Exiting The Gasifier (Wet Basis) | 69 |
4.7 | Composition of Inlet Stream Into Quencher | 74 |
4.8 | Composition of Outlet Stream from Quencher | 75 |
4.9 | Equilibrium Data for CO at Different Temperatures | 80 |
4.10 | Catalyst Properties of Chromium Promoted Iron Catalyst | 82 |
4.11 | Reactor Dimensions of Catalytic Converter | 84 |
4.12 | Composition of Inlet and Outlet Streams for CO2 Removal | 93 |
4.13 | Equilibrium Data for CO2 Removal | 94 |
4.14 | Summary of CO2 Absorber Dimensions | 95 |
4.15 | Summary of Proposed Heat Exchanger Design | 96 |
4.16 | Heat Transfer Coefficients with Corresponding Area And Face Velocity Values | 105 |
4.17 | Corresponding Face-Area and Face-Velocity Values | 106 |
4.18 | Approximate Frictional Pressure Drop Across Process | 111 |
5.1 | Tensile Strength Values At Different Temperatures | 119 |
5.2 | Design Stress Values at Different Temperatures | 120 |
6.1 | Hazop Analysis for Gasifier | 138 |
6.2 | Hazop Analysis or Waste Heat Boiler | 139 |
6.3 | Hazop Analysis for Heat Exchangers | 140 |
6.4 | Hazop Analysis for Initial H2s Removal | 141 |
6.5A | Hazop Analysis for Saturator | 145 |
6.5B | Hazop Analysis for Desaturator | 146 |
6.5C | Hazop Analysis for Lines 1 And 2 | 146 |
6.6A | Hazop Analysis for Co2 Removal Inlet | 147 |
6.6B | Hazop Analysis for Co2 Removal Outlet | 148 |
6.7 | Hazop Analysis for Storage Tanks | 149 |
6.8 | Flammability Limits of Different Compounds | 155 |
7.1 | Inflation Rates By Month And Year (1999-2011), US Inflation Calculator | 159 |
7.2 | Refractory Brick Density Calculation | 160 |
7.3 | Inflation Rates By Month And Year (2005-2011) (For Bare Vessel) | 161 |
7.4 | Inflation Rates By Month And Year (2005-2011) (For Packing Material) | 162 |
7.5 | Inflation Rates By Year (2005-2011) ( For H2s Removal Vessel) | 165 |
LIST OF FIGURES
FIGURE | TITLE | PAGE |
2.1 | Shell Oil Gasifier | 12 |
2.2 | The Quenching Unit As Conditioned By Design Specifications | 18 |
2.3 | Schematic Diagram of a Packed Column | 19 |
2.4 | Structure of Sterically Hindered Amines | 23 |
2.5 | Adiabatic Stages in Water Gas Shift Reaction | 26 |
2.6 | Schematic Diagram Of Final H2s Removal Stage | 32 |
2.7 | Benfield Process For Co2 Removal | 38 |
2.8 | Ram Pump Schematics | 39 |
2.9 | Ram Pump Schematics | 40 |
2.10 | Ram Pump | 41 |
2.11 | Air-Cooled Exchangers | 44 |
2.12 | Finned Tubes | 45 |
2.13 | A Plate Heat Exchanger | 46 |
2.14 | Assemblage Of Baffles And Tubes Inside A Shell And Tube Heat Exchanger | 48 |
2.15 | Counter-Current Flow In A Heat Exchanger And The Temperature Profile Within The Exchanger | 48 |
2.16 | Co-current Flow Through A Heat Exchanger With The Temperature Profile Through The Equipment | 49 |
4.1 | The Heavy Fuel Oil Gasifier | 64 |
4.2 | The Quencher | 72 |
4.3 | The Initial H2S Scrubber | 77 |
4.4 | The CO Catalytic Converter | 79 |
4.5 | The Final H2S Remover | 85 |
4.6 | CO2 Removal | 92 |
4.7 | Air-Cooled Exchangers | 103 |
4.8 | Finned Tubes | 104 |
5.1 | Skirt Support | 128 |
5.2 | Double Plate With Gusset | 128 |
5.3 | Physical Layout Of A 2-Tube Pass Shell And Tube Exchanger | 137 |
7.1 | Cost Estimation Data For Shell And Tube Heat Exchangers | 168 |
LIST OF SYMBOLS
2S left in output stream
B = amount of H2S removed from aP3
We are told that the H2S is scrubbed to 15ppm
aP3 = 0.0201Kmol/hr
so that
0.5 = 0.02011 + b
B = 0.4799 Kmol/hr
TABLE 3.1: COMPOSITION BEFORE H2S REMOVAL
components | Kmol | Kmol % |
H2 | 47.6 | 671.636 |
Co | 42.1 | 594.031 |
Co2 | 8.3 | 117.113 |
N2 | 1.40 | 19.754 |
CH4 | 0.1 | 1.411 |
H2S | 0.5 | 7.055 |
1411 |
TABLE 3.2: COMPOSITION AFTER H2S REMOVAL
components | Kmol | Kmol % |
H2 | 671.636 | 47.839 |
Co | 594.031 | 42.311 |
Co2 | 117.113 | 8.342 |
N2 | 19.754 | 1.401 |
CH4 | 1.411 | 00.1005011 |
H2S | 0.02011 | 0.001432 |
1403.9651 | 100.0000 |
From here, the scrubbed gas moves on to the water gas shift reactor, where CO is used up and H2, CO2 are produced.
Now, onto the CO conversion stage. The reaction stoichiometry ofWater gas shift is:
CO + H2O = CO2 + H2
Assuming 99.8% conversion was obtained from the simulation we can obtain the composition of the output from the 2nd stage CO conversion:
Overall conversion =
0.998 =
Where aP5 is the molar flow of CO out of the WGS reactor.
aP5 = 1.881Kmol
Amount of CO reacted = 594.031 – 1.881
= 592.8429 Kmol
Also, using the reaction stoichiometry,
Amount of CO produced = 592.8429 Kmol
Amount of H2 produced = 592.8429 Kmol
Amount of H2O reacted = 592.8429 Kmol**
** is the total amount of water reacted. From the problem statement, we now that this is made up of water from the gasification process from the saturation and from the water fed into the WGS Reactor.
An oxygen atom balance around the Reactorshould tell exactly how much of this water came from the gasified and this will be done later.
TABLE 3.3: COMPOSITION OUT OF THE WGS REACTOR
Components | Kmol | Kmol % |
H2 | 1264.4789 | 63.3335 |
CO | 1.1881 | 0.05951 |
CO2 | 709.9559 | 35.5593 |
N2 | 19.754 | 0.9894 |
CH4 | 1.411 | 0.0707 |
H2S | 0.02011 | 0.001007 |
1996.541 | 100.001 |
From here, the gas mixture moves to the final H2S removal stage, where H2S is scrubbed to less this 1ppm. Assuming scrubbing of H2S to 0.8ppm,
TABLE 3.4: FINAL H2S REMOVAL OUTLET
Components | Kmol |
H2 | 1264.4789 |
CO | 1.1889 |
CO2 | 709.9559 |
N2 | 19.754 |
CH4 | 1.411 |
H2S | 1.06583 x 10-3Kmol |
We are required to produce 750,000 stdm3/day of feed i.e. 31250 stdm3/hr. Using the ideal gas relation, this is equivalent to 1277.92 Kmol /hr
Using this, we can calculate the % composition of all constituent except Co2, since there are molar flows are already fixed
Table 3.5: PERCENTAGE COMPOSITION OF CONSTITUENTS FROM FINAL H2S REMOVAL OUTLET
H2 | 98.00% |
Co | 1.1889% |
N2 | 1.55% |
CH4 | 0.1104% |
H2S | 0.0000834% |
CO2 = 100 – (98.00 + 0.093 + 1.55 + 0.1104 + 0.0000834)
= 0.247%
Molar flow of CO2 = x 1277.92
= 3.1503 Kmol /hr
To obtain feed flow rate:
Moles of C in quenched gas
= 591.636 () + 117.113 (
) + 1.411 (
)
=287.842 Kmol of carbon
= 3454.104 kg
The mass of C calculated above amounts to 98.5% of the total carbon in the feed. Using this information, we can calculate the total weight of the Carbon in feed
0.985 C = 3454.104
C = 3506.705Kg
Now, we can calculate the total weight of feed:
85 wt. % of feed is carbon
0.85 (F) = 3506.705kg
F = 4125.535kg/hr feed
We can also calculate the flow rate of steam and air:
Mass of steam = 0.75 (1125.535)
= 3094.1511kg/hr
Now,
4125.535kg = +
+
= 751.1912 kmol/hr
1.16kg of O2 = 0.03625 mole of O2
1.16kg of O2 = 0.03625 mol of O2/0.1821 mol feed
So that:
Total mole of (impure) feed =
= 149.551 mol of impure O2
Actual mole of O2 fed = 0.95 (149.551)
= 142.073 moles of O2
= 4546.34kg of O2
3.2 ENERGY BALANCE AROUND CO CONVERSION STAGE
TABLE 3.6 COMPOSITION OF THE INLET INTO THE CO CONVERSION STAGE
COMPONENT | COMPOSITION (Kmol) | Tref (K) | Href (J/gmol) | H380 | ∆H | MiHi |
H | 671.636 | 298 | 718 | 10977.2 | 10259.2 | 6890448.051 |
CO | 594.031 | 298 | 728 | 11243.5 | 10515.5 | 6246532.981 |
C02 | 117.113 | 298 | 912 | 16200.5 | 15288.5 | 1790482.101 |
N2 | 19.254 | 298 | 728 | 11099.5 | 10371.5 | 199692.861 |
CH4 | 1.411 | 298 | 879 | 16800.5 | 15921.5 | 22465.237 |
H2S | 0.02011 | 298 | 845 | 13522.3 | 12677.3 | 254.941 |
H2O | 553438 | 298 | 837 | 13072.2 | 12235.2 | 653824617.6 |
TOTAL | 668.97 ˣ 106 |
TABLE 3.7 COMPOSITION OF THE OUTLET FROM THE CO CONVERSION STAGE
COMPONENT | COMPOSITION (Kmol) | Tref (K) | Href (J/gmol) | H380 | ∆H | MiHi |
H | 1264.4789 | 298 | 718 | 10988.5 | 10278.5 | 12986830.54 |
CO | 1.1888 | 298 | 728 | 11206.5 | 10478.5 | 12449.505 |
C02 | 702.9559 | 298 | 912 | 16231.5 | 15319.5 | 10768.93291 |
N2 | 19.754 | 298 | 728 | 11139.5 | 10411.5 | 205668.771 |
CH4 | 1.411 | 298 | 879 | 16819.5 | 15940.5 | 22492.0455 |
H2S | 0.02011 | 298 | 845 | 13729 | 12884 | 259.097 |
H2O | 52854 | 298 | 837 | 13171 | 12334 | 651901.236 |
TOTAL | 675652768.9 |
To obtain the heat of reaction with respect to H2 produced,
= (1264.4789 – 671.636) × (- 4.2 × 104 KJ/hr Kgmol)
= 5928429Kgmol × 4.2 × 104 KJ/ Kgmol
= – 24.899 × 106 KJ
Q = 0H0 –
1H1 + ∆Hrn
= (675.652 × 106 – 668.97 × 106) + (- 24.899 × 106)
= – 18.217 × 106 KJ/hr
A total of 18.217 × 106 KJ/hr of heat is given off in the CO conversion unit. This large amount of heat was utilised in the preheating of the unconverted gas in heat exchanger
The Geeral energy balance equation reduces to
ASSUMPTIONS
The enthalpy content of the crude gas leaving the gasifier is majorly due to the gasification reaction, which is:
But,
Ignoring all side reactions, the calorific value for the gasification reaction is equal to 4.29 x 107KJ/Kg
The reference temperature of 50% is chosen for convenience, the general energy balance equation becomes;
TABLE 3.8: ENERGY BALANCE OF OUTLET STREAM FROM GASIFIER
Composition | Kgmol | Tref | Href,
J/gmol |
H1573
J/gmol |
![]() |
moHo |
H2 | 671.636 | 323 | 1485.25 | 39064.25 | 37579 | 25.24 x 106 |
CO | 594.031 | 323 | 1514.25 | 41796.75 | 40282.5 | 23.93 x 106 |
CO2 | 117.113 | 323 | 1965.25 | 66368.25 | 64403 | 7.54 x 106 |
N2 | 19.754 | 323 | 1513.25 | 41343.75 | 39830.5 | 786.81 x 103 |
CH4 | 1.411 | 323 | 1897.5 | 81440.75 | 79543.25 | 112.24x 103 |
H2S | 7.055 | 323 | 1749.75 | 54078 | 52303.25 | 369.0 x 103 |
H2O | 94.031 | 323 | 1749.75 | 51823.75 | 50074 | 29.74 x 106 |
C | 323 | – | – | – | 87.72 x 106 |
TABLE 3.4 ENERGY BALANCE OF INLET STREAM TO GASIFIER
Htrh | Tref | Href,
J/gmol |
H1573
J/gmol |
![]() J/gmol |
miHi | moHo |
O2 | 323 | 1530.5 | 68.11 | 5280.5 | 1.95 x 106 | 369.07 |
N2 | 323 | 1513.25 | 6644 | 5130.75 | 99.66 x 103 | 19.425 |
H2O | 323 | 1749.75 | 7752 | 6002.25 | 1.03 x 106 | 171.90 |
3.080 x 106 |
is considered here to be the calorific value of the fuel oil
= 87.72
CHAPTER FOUR
4 CHEMICAL ENGINEERING DESIGN
The feed storage tank farm will be designed in such a way that each tank will be able to hold about 5 days of feed in storage. There will be a total of ten feed storage tanks in the tank farm
- The tank is a vertical, cylindrical shaped storage tank with a fixed and floating roof
- Floating roof rises and falls with the liquid level inside the tank, thereby decreasing the vapor space above the liquid level. They are considered a safety requirement as well as a pollution prevention measure.
- A vertical tank is preferred over a horizontal tank since it takes up less space, is easily supported on concrete slabs and allows maximum mixing.
- The storage tanks are supported with a skirt support as they do not impose concentrated loads on the vessel shell
- A drain line is installed so that water at the bottom of the tank (caused by the difference between the internal and external temperature) can be regularly removed.
TABLE 4.1: TANK 1 DIMENSIONS
Top of shell height | 100% | 23.21m |
Design fill level | 95% | 22.05m |
Normal fill level | 85% | 19.73m |
Minimum fill level | 35% | 8.12m |
Bottom of shell height | 0% | 0 |
This tank is similar to tank in function, configuration, material of construction and safety devices and structural supports used. The only difference is that it is a smaller tank used to aid the Start-up and shut down procedures. This tank is required to store enough heavy fuel oil for a 3 hour production run.
TABLE 4.2: TANK 2 DIMENSIONS
Top of shell height | 100% | 6.75m |
Design fill level | 95% | 6.41m |
Normal fill level | 85% | 5.74m |
Minimum fill level | 35% | 2.36m |
Bottom of shell height | 0% | 0m |
This tank is used for the storage of the final product gas, hydrogen before it is supplied to the immediate consumers. They are designed as spherical tanks since this shape is more ideal for storage of the gaseous product.
TANK DIMENSIONS
For each of the 50 tanks, assume that H = 3D
Similar to tanks 1 and 2, there are safety allowances in the height of the tank.
So that D = 44m
Installed storage capacity is now
TABLE 4.3: TANK STORAGE CAPACITIES
TANK | STORAGE CAPACITY |
TANK 1 (FEED STORAGE TANK) | 531.25m3 |
TANK 2 (FRESH FEED SURGE DRUM) | 13.281m3 |
TANK 3 (PRODUCT STORAGE TANK) | 75000m3 |
FIGURE 4.1 THE HEAVY FUEL OIL GASIFIER
The following reactions take place in the gasifier:
(4.4.1)
(4.4.2)
(4.4.3)
(4.4.4)
(4.4.5)
The slowest reaction is reaction 4.4.4 (Carbon-steam reaction) and is therefore taken as the rate determining step for the reactor.
C + H2O → H2 + CO (rate-determining step)
The rate expression for this reaction is given as:
r = kv
Where:
r = rate of reaction (in this case, the rate of disappearance of H2O)
kv = rate constant
K = equilibrium constant
CH2O, CH2 and CCO = molar concentrations of CH2O, CH2 and CCO respectively (kmol/m3)
Given the table below for rate constant, kv (from reference source)
TABLE 4.4 RATE CONSTANT VALUES AT SPECIFIC TEMPERATURES
T (K) | 952.38 | 1000 |
kv (cm3/gmol.s) | 1.62 | 8.6 |
TABLE 4.5 COMPOSITION OF CRUDE GAS EXITING THE GASIFIER (WET BASIS)
COMPONENTS | AMOUNT (kmol/hr) | COMPOSITION |
H2 | 671.636 | 0.4232 |
CO | 594.031 | 0.3743 |
CO2 | 117.113 | 0.0738 |
CH4 | 1.411 | 0.0008 |
H2O | 171.01 | 0.1077 |
H2S | 7.055 | 0.0044 |
N2 | 19.754 | 0.0124 |
C | 5.16 | 0.0033 |
Total | 1587.17 | 1.0000 |
Height of the gasifier = 9.64 m
Diameter of the gasifier = 1.99 m
Total molar flow rate of the exit crude gas = 1587.17 kmol/hr
Volumetric flow rate of the exit crude gas = =3347.88 m3/hr
Residence time, τ = Volume/Volumetric flow rate = = 0.0089 hr = 32.13s
Space velocity, υ = 1/ τ = 1/32.13s = 0.031 s-1
The waste heat boiler will be designed as a special type of shell and tube heat exchanger called a water tube waste heat boiler, initially mentioned in the previous semester’s work. The water tube design is a very difficult one to obtain but has been selected because of its ability to withstand very large pressure generation like the one specified in this design. Additional energy recovery and fuel conservation can be realized with the use of the water tube boiler, by adding a boiler feed water economizer to the boiler design.
Before we start designing the exchanger, we need to determine the heat duty of the demineralised feed water i.e how much heat it will be required to absorb from the hot flue gas stream.
The calculations leading to the determination of in the above equation are shown below:
Cp-values are dependent on temperature, so we have to determine the Cp of all the individual components that make up the inlet stream (i.e. at 1300°C)
The heat capacity equations are:
C: Cp = 11.18 + 1.095 × 10-2 – 4.891 × 105
-2
H2: Cp =
CO: Cp =
CO2: Cp =
N2: Cp =
CH4: Cp =
H2S: Cp =
Using these Cp values, we can calculate a bulk Cp for the stream as shown:
TABLE 4.6: BULK CP VALUES FOR STREAM COMPONENTS
COMPONENT |
Cp (J/KMOLOC)
|
MOLE FRACTION |
MOLAR FLOW |
IN-STREAM Cp (J/KMOLOC) |
C | 28.207 | 0.00362 | 5.157 | 0.2089 |
H2 | 32.585 | 0.47191 | 671.636 | 13.2328 |
CO2 | 58.747 | 0.08229 | 117.113 | 4.1593 |
CO | 35.412 | 0.41739 | 594.031 | 12.7199 |
N2 | 35.222 | 0.01388 | 19.754 | 0.4191 |
CH4 | 135.761 | 0.00099 | 1.411 | 0.1222 |
H2S | 51.4787 | 0.00496 | 6.702 | 0.0360 |
From the addition of all the values in the in-stream Cp column, we obtain:
Cp = 35.92522 J/mol. °C
Substitute the value of Cp above into Equation (2.1):
From the material balance calculations, we can see that
Inside heat transfer coefficient:
hi = 1309379.395 W/m2k
Outside heat transfer coefficient
ho = 2000Btu/ ho ft2oF
= 11333.33W/ m2oC
Overall heat transfer coefficient:
Heat transfer area:
Mean temperature difference:
MTD =
Number of tubes:
Tube lunght, L:
Tube pitch: Pi =
shell diameter: = 1.6646m
Pressure drop (shell side):
Pressure drop (tube side):
Shell wall thickness determination:
Pi= 3000 kPa
Di = 1.078 m
At the shell side mean temperature of 189.21oC,
f = 134 × 106N/m2
Therefore,
e = 3000000( 1.078)/ [2(134 × 106) – 3000000]
= 12.2 mm
Other design specifications include:
- Design Pressure = 110% of operating Pressure = 3300 kPa
- Design temperature = Maximum shell temperature = 220oC
- Corrosion Allowance = 4 mm
FIGURE 4.2 THE QUENCHER
The quencher is designed as a packed column, so as to increase the contact area between the gas and the water and thus allow for efficient removal of residual carbon from the gas stream.
4.6.1 Design Procedures
The design of a packed column will involve the following steps:
1. Select the type and size of packing.
2. Determine the column height required for the specified separation.
3. Determine the column diameter (capacity), to handle the liquid and vapour flow rates.
4. Select and design the column internal features: packing support, liquid distributor, redistributors.
4.6.2 Types of Packing
The principal requirements of a packing are that it should:
- Provide a large surface area: a high interfacial area between the gas and liquid.
- Have an open structure: low resistance to gas flow.
- Promote uniform liquid distribution on the packing surface.
- Promote uniform vapour gas flow across the column cross-section.
Random packing and structured packing elements are more commonly used in the process industries.
DATA GIVEN
Exit Gas stream composition
Moles of exit and inlet gas stream
From material balance, input and exit gas stream composition is calculated.
DATA REQUIRED
Heat Capacity
Amount of water required to achieve the desired temperature change
Tower Diameter
Tower Height
TO OBTAIN MASS OF COOLING WATER REQUIRED:
Heat lost by crude gas= heat gained by cooling water
Entering Crude gas temperature=250oC
Exiting Crude gas temperature=50oC
Entering Temperature of cooling water= 25oC
Exiting temperature of the cooling gas= this is assumed to be 90oC
Inlet Stream Into Quencher
TABLE 4.7: COMPOSITION OF INLET STREAM INTO QUENCHER
COMPONENT | MOLE (Kmol) | MOLE FRACTION |
C | 5.16 | 0.00364 |
H₂ | 671.636 | 0.4743 |
CO | 594.031 | 0.4195 |
CO2 | 117.113 | 0.0827 |
N₂ | 19.754 | 0.01395 |
CH₄ | 1.411 | 0.000996 |
H₂S | 7.055 | 0.00498 |
1416.16 |
4.6.3 HEAT CAPACITY
The heat capacity data can be obtained from heat capacity tables in available from literature
Taking a reference temperature of 15oC.
The heat capacity equations are:
C: Cp = 11.18 + 1.095 × 10-2T – 4.891 × 105T-2
H2: Cp =
CO: Cp =
CO2: Cp =
N2: Cp =
CH4: Cp =
H2S: Cp =
TABLE 4.8: COMPOSITION OF OUTLET STREAM FROM QUENCHER
COMPONENT | MOLE (Kmol) | MOLE FRACTION |
H₂ | 671.636 | 0.476 |
CO | 594.031 | 0.421 |
CO₂ | 117.113 | 0.083 |
N₂ | 19.754 | 0.014 |
CH₄ | 1.411 | 0.001 |
H₂S | 7.055 | 0.005 |
1411 |
Heat lost by the crude gas, ΔH is given by
net dT
= 1039.525 KJ/Kmol
ΔHnet = (6984.618 × 1416.16) – (1039.525 × 1411) KJ/hr
= 2,340.157 KJ/s
Heat gained by the water = m
= 96,189.91 KJ/Kmol
Thus, Heat gained by water = (m/M x 96189.91KJ/Kmol)
Molecular weight of water = 18 Kg/Kmol
Heat gained by water = 96189.91/18 m = 5343.88 m
Since, heat lost by the crude gas = heat gained by water
Therefore,
5343.88m = 2340.157
m = 0.438 Kg/s
Allowing a minimum of 10 minutes hold-up of water,
Therefore, m = 0.438 Kg/s x 10mins x 60s = 262.748 Kg
4.6.4 COLUMN DIAMETER
D = (4S/π)1/2
= (4 × 0.2185/3.1429) ½
= 0.5275 m
4.6.5 HEIGHT OF THE COLUMN: Z
This is obtained, from Coulson and Richardson, using the following formula:
Z= HOGNOGS.F
= 3.0893 m
FIGURE 4.3 THE INITIAL H2S SCRUBBER
4.7.1 ASSUMPTIONS
- No NMP in Output gas stream
- Unit operates at 50% of the flooding gas mass velocity
- Flow rate of NMP is 40% more than the minimum
Given that
Henry’s law constant for NMP = 0.97
Density of gas stream = 31.49kg/m3
Density of NMP = 1020kg/m3
H2S concentration in the inlet stream = 0.5mol%
NMP has already been selected from the first semester preliminary design as our scrubbing liquid.
An energy balance is not require for this unit because there is very little temperature change between the unit’s inlet and exit streams and hence the unit can be assumed to be operating isothermally.
A packed column using 1 in. Raschig ring packing with a packing factor of 160 have been selected for use for this design. Raschig rings have been selected because they give a larger degree of contact between the gas phase and the liquid phase. It also gives a higher mass transfer area to work with.
Column height = 14m (approx.)
Column diameter = 2.44m (approx.)
FIGURE 4.4 THE CO CATALYTIC CONVERTER
This unit converts carbon monoxide to carbon dioxide, a reaction which leads to the production of more hydrogen. It is required to carry out this reaction over chromium-promoted iron oxide catalyst. The catalyst vessel is a single shell with a dividing plate separating the two catalyst beds which constitute the two stages of conversion. The following reaction takes place in the CO catalytic converter:
CO + H2O CO2 + H2 ΔH= – 41170.51J
Also provided are the basic data for the CO conversion section of the plant:
- Space velocity
The space velocity through each catalyst stage be assumed to be 3500 volumes of gas plus steam measured at NTP per volume of catalyst per hour. It should further be assumed that use of this space velocity will allow a 10°C approach to equilibrium to be attained throughout the possible range of catalyst operating temperatures listed below.
- Equilibrium data for the CO conversion reaction
TABLE 4.9 EQUILIBRIUM DATA FOR CO AT DIFFERENT TEMPERATURES
TEMP/K | 600 | 700 | 800 | |||
KP | 3.69 x 10-2 | 1.11 x 10-4 | 2.48 x 10-4 |
In the design of a catalytic converter, the following are the key issues to be considered: reactor type; catalyst type, catalyst volume and mass; the catalytic converter sizing; operating conditions (temperature and pressure) within the reactor; phase type; feed conditions (temperature and concentration).
4.8.1 Reactor Type: Fixed Bed Reactor
The fixed bed reactor is a tubular which is packed with solid granular catalyst on a fixed support. It is termed a fixed bed reactor because the reactor feed, whether liquid or gaseous feed passes through the catalyst bed to contact with the catalyst for chemical reactions, with the catalyst bed not being moved as the fluid flows feed through it. Based on the flow directions of the feedstock some of the hydro – processing reactors can be divided into “axial” reactors and “radial” reactors. In the axial reactor the feed flows along the axial direction for the reactions to take place. Generally the feed flows downwards. In the radial reactor the feed flows in the radial direction for the reactions to take place. The axial reactor is used when the pressure drop across a catalyst bed is small. Or otherwise the radial reactor should be used. Based on the temperature of the cylindrical shell some reactors can be divided into cold wall reactors and hot wall reactors. They are all fixed bed reactors. “Hot wall” reactor is not lined with any heat insulating linings. Because the temperature of the reactor shell is very high, the reactors must be made of alloy steel which can sustain high temperature and is highly resistant to hydrogen corrosion. The advantage is that more volume of such a reactor can be effectively used. A “cold wall” reactor is lined with heat-insulating material. The temperature of the reactor shell is quite low, ordinary low alloy steel can be used for making such reactors. Corrosion caused by feedstock, especially by hydrogen can be avoided.
4.8.2 Catalyst: Chromium – Promoted Iron Oxide
The overall reaction of a heterogeneous gas-solid reaction on a supported catalyst, such as the one involved in this design, is made up of a series of physical steps as well as the chemical reaction. First, there is mass transfer of reactant from the bulk gas phase to the external solid surface, after which there is diffusion from the solid surface to the internal active sites, activation of the adsorbed reactants; next is the most important step of chemical reaction, then desorption of products, internal diffusion of products to the external solid surface, and mass transfer to the bulk gas phase.
TABLE 4.10: CATALYST PROPERTIES OF CHROMIUM PROMOTED IRON CATALYST (Source: Chemical Reactor Design for Process Plants by Howard F. Rase, 1999)
PROPERTY | CHROMIUM – PROMOTED IRON OXIDE |
Maximum operating Temperature (K) | 890 0F |
Tablet size | ![]() |
Bulk Density | 70 lb / cu ft |
Particle Density | 126 lb / cu ft |
Cost | 20 $ / cu ft |
Catalyst poisons | Inorganic salts, boron, oils or phosphorus compounds, liquid H20 is a temporary poison. Sulfur compounds in an amount greater than 50 ppm |
Catalyst life | 3 years and over depending on care in startup and during operation |
The purpose of the chromium promotion is to minimize catalyst sintering by textural promotion. During the course of the reaction, there are no significant side reactions.
The works of Xue et al confirm that Carbon is formed if the water-gas shift reaction occurs at the reaction stoichiometry and temperature. In order to achieve higher conversions with the use of a catalyst and also avoid coking, the H2O / CO feed ratio must be higher than that required by the reaction stoichiometry. With this low H2O / CO ratio, all possible side reactions would likely produce C or CH4. Formulation of C blocks the catalyst sites causing catalyst deactivation and an increase in the pressure drop across the bed caused by plugging or fouling of the reactor. Formation of CH4 would consume the hydrogen and alter the product composition which may give rise to potential difficulties in subsequent processes.
Activated Fe3O4 is pyrophoric, that is, it ignites spontaneously upon exposure to air, and as a result the catalyst must be re-reduced and stabilized by surface oxidation (using an inert gas with a low concentration of O2) before being re-used.
4.8.2.1 Catalyst Volume (from space velocity):
The catalyst volume can be obtained from space velocity data given in the problem statement coupled with the simulation figures for the flowrate of gases into the catalytic converter.
FOR 1ST STAGE:
4.8.2.2 Catalyst Mass (in 1st stage of converter):
FOR 2ND STAGE:
4.8.2.3 Catalyst Mass (in 2nd stage of converter):
4.8.3 CATALYTIC CONVERTER SIZING
In carrying out the sizing of Fixed Bed Reactors, most designs approximate to plug flow. The simplest of such arrangements is adiabatic (Chemical Process Design and Integration by Robin Smith).
A summary of the reactor dimensions is provided in the table that follows.
TABLE 4.11: REACTOR DIMENSIONS OF CATALYTIC CONVERTER
CATALYST BED | LENGTH(M) | DIAMETER(M) | VOLUME(M3) |
1st Stage | 7.03 | 3.518 | 68.34 |
2nd Stage | 12.22 | 3.518 | 118.83 |
REACTOR | |||
1st Stage | 8.795 | 3.518 | 85.50 |
2nd Stage | 14.61 | 3.518 | 142.06 |
Total | 23.405 | 3.518 | 227.56 |
FIGURE 4.5 FINAL H2S SCRUBBER
The process:
The final H2S removal stage could be divided into two operations namely:
- Normal operation
- Intermittent regeneration operation
4.9.1 NORMAL OPERATION
The converted gas leaving an air-cooled heat exchanger is fed to the unit together with oxygen. Iron oxide in the Lautamasse reacts with hydrogen sulphide in the converted gas to form iron sulphide. The iron sulphide is an intermediate product and it reacts with the oxygen as quickly as it is formed to produce iron oxide and sulphur deposits. This process occurs continuously and is represented by the equation.
2Fe2O3(s) + 6H2S 2Fe2S3 + 6H2O
2Fe2S3 + 3O2 2Fe2O3 + 6S
4.9.2 REGENERATION OPERATION
When the quantity of sulphur deposit overtime attain a value between 40 55% of the dry weight of the Lautmasse, the normal process will be stopped. Hot oxygen only is then continuously fed to the unit in a parallel in order to oxidize the sulphur deposit to sulphur(iv) oxide gas which can be converted to tetraoxosulphate(vi)acid in order to generate money.
S(s) + O2(g) SO2(g)
The Lautamasse becomes ineffective when the regeneration process has been carried out for about 10times.
4.9.3 THE EQUIPMENT
The final H2S removal is to take place in
- Four vertical vessels
- A separate outlet from each of the vessel converging SO2 from regeneration
- A separate inlet header to each of the column, conveying heated oxygen.
- A minimum point where the oxygen and the converted gas is mixed.
- Each column contains five trays each containing Lautamasse
- The columns are to be identical.
The following was specified
- Height of column = 18.5 m
- Diameter of column = 2.5 m
- Number of trays = 5
- Total pressure drop = 35 KN/m2
- Number of columns = 4
- Locking lid type = Autoclave
Unspecified Parameter are:
- Plate type and its configuration
- Mass of iron oxide per tray
- Regeneration period
- Regeneration duration
- Tray thickness
- Tray spacing
Choice of tray – Bubble cap
Reasons:
- It provides maximum contact between the gas and solid unlike the sieve and valve trays.
- It allows for maximum occupation of the tray space volume by the Lautamasse powder.
- The riser hole size – 5 mm (Coulson and Richardson )
- Choice of material : Low alloy steel (Ni, Cr, Mo, V)
Properties
Tensile strength – 550 N/mm2
Design stress – 240 N/mm2
- Determination of number of holes
N = 25001 holes
(e) Determination of the mass of lautamasse and sulphur.
= 10402.6 Kg
When the quantity of sulphur deposit on the tray falls between 40-55% of the weight of the lautamsee the operation has to be stopped and then regeneration takes place.
Assuming the mass of sulphur and the lautamase is the ratio 1:0.4 that is assuming that sulphur is 50% of the total mass mixture.
Mass of sulphur
=3467.5kg
Mass of fe203 =
=6935kg
To calculate the time for regeneration:
4.9.4 ASSUMPTION
The absorption of H2S in the four columns are 50%, 30%, 20%, 10%. The assumption is based on the fact that absorption decreases along the column. But we want to model the column base on the absorption of the first column.
Time after which regeneration will take place is
=15.8months
16months
After 16 months regeneration process has to be carried out.
Volume and height of sulphur and lautamasse determination.
Mass of sulphur = 3467.6kg
Density of sulphur = 2000kg/m3
Volume of sulphur =
=
Height =
=
= 0.3532m
Lautamasse;
Density of lautamasse = 675kg/m3
Mass of lautamasse = 6935kg
Volume =
= 10.274m3
Height =
= 2.0930m
This is a good value since the higher the height of the lautamasse, the lesser the effective tray spacing.
Total height of lautamasse and sulphur
= 2.0930 + 0.3532
= 2.45m
4.9.5 REGENERATION
Sulphur deposit after 16months per column = 3467.5kg 5
= 17337.5kg
Amount in moles=
= 541.797 moles
S + O SO2
541.8 kmol of O2is required per column.
Since each column is designed assuming 50% of the total H2S absorbed
(4 541.797kmol)SO2 = 150% of the actual SO2 produced
Also, (4 541.797kmol)SO2 = 150% of the oxygen required
The actual SO2 produced = 1444.8kmol
The actual O2 required = 1444.8kmol
If regeneration is assumed to take place within 6hrs,
Flow rate of SO2 regenerated = 240.8kmol/hr
FIGURE 4.6 CO2 REMOVAL
Mechanism of Removal: Absorption
Absorption Mechanism: Chemosorption(Chemical Absorption)
Equation of Reaction
K2CO3(aq) + H2O(l) + CO2(g) 2KHCO3(aq)
Basis : 4125.535 kg of Feed / hr
TABLE 4.12: COMPOSITION OF INLET AND OUTLET STREAMS FOR CO2 REMOVAL
COMPONENT | yin | yout |
H2 | 0.63326 | 0.9800 |
CO | 0.00060 | 0.00093 |
C02 | 0.35555 | 0.00247 |
N2 | 0.00989 | 0.0155 |
CH4 | 0.00071 | 0.001104 |
H2S | 5.33E-07 | 8.34E-07 |
TOTAL | 1.000000 | 1.000000 |
ASSUMPTION: Only Carbon dioxide (CO2)is absorbed and all the other gases act as inert in the 40% K2CO3 solution.
Mole Ratio Of Co2 In The Gas Entering The Column
Mole Ratio Of Co2 In The Gas Leaving The Column
Plotting the equilibrium curve for CO2
TABLE 4.13: EQUILIBRIUM DATA FOR CO2 REMOVAL
![]() |
X | Y | X | Y |
0.025 | 0.1 | 0.0017 | 0.111111 | 0.001703 |
0.18 | 0.2 | 0.0122 | 0.25 | 0.012351 |
0.6 | 0.35 | 0.0408 | 0.538462 | 0.042535 |
1.7 | 0.5 | 0.1156 | 1 | 0.13071 |
4.0 | 0.68 | 0.2722 | 2.125 | 0.374004 |
7 | 0.75 | 0.4762 | 3 | 0.909126 |
10 | 0.8 | 0.6803 | 4 | 2.127932 |
11 | 0.9 | 0.748 | 9 | 2.968254 |
4.10.1 PACKING MATERIAL: Pall Rings (Plastic)
Pall rings are chosen as the Fp (Packing Factor), small column diameter, high quality with low price, low pressure drop.
The packing characteristics
Dp = 90mm
% = 92%
Summary of design
TABLE 4.14: SUMMARY OF CO2 ABSORBER DIMENSIONS
COLUMN DIAMETER | 1.3m |
COLUMN HEIGHT | 24.96m |
PACKING TYPE | Plastic pall rings |
DIAMETER OF PACKING | 90mm |
VOIDAGE | 92% |
SPECIFIC AREA | 85m2/m3 |
PACKING FACTOR | 17.07 ft-1 |
QTY OF SOLVENT REQUIRED | 852.537 kmol/hr |
- HEAT EXCHANGER DESIGN
4.11.1 THE PROPOSED DESIGN
TABLE 4.15: SUMMARY OF PROPOSED HEAT EXCHANGER DESIGN
EXCHANGER | FIRST | SECOND |
Tube Layout | Split ring, floating head, 1 shell pass, and 1 tube pass of4.83 m length, 30 mm O.D., 26 mm I.D., and triangular pitch. Pitch-to-diameter ratio of 1.25 | Split ring, floating head, 1 shell pass, and 4 tube passes of6.00 m length, 20 mm O.D., 16 mm I.D., and triangular pitch. Pitch-to-diameter ratio of 1.25 |
Total number of Tubes/Number of Tubes per pass | 96/96 | 1308/327 |
Heat transfer area (based on outside diameter)m2 | 43 | 493 |
Shell Internal diameter (mm) | 484.5 | 1064.4 |
Baffle spacing (mm) | 97 | 212.88 |
Baffle cut | 25% | |
Tube-side coefficient (W/m2 °C), clean. | 252.97 | 102.42 |
Overall coefficient, estimated (W/m2 °C). | 120.00 | 60.00 |
Overall coefficient required (W/m2°C). | 149.85 | 67.81 |
Dirt/Fouling factors
Tube-side/Shell-side(m2 °C /W) |
0.0002 /0.0003 | 0.0002 /0.0003 |
Pressure drops, including drop over nozzles (estimated)
Tube-side/Shell-side (kPa) |
253/452 | 73/969 |
4.11.2 OPTIMISATION
There is scope for optimizing the design by reducing the number of tubes, as the pressure drops are well within specification and the overall coefficient is well above that needed. However, the method used for estimating the coefficient and pressure drop on the shell side(Kern’s method) is not so accurate, so keeping to this design will give some margin of safety.
4.11.3 VISCOSITY CORRECTION FACTOR
The viscosity correction factor was neglected when calculating the heat transfer coefficients and pressure drops. This is reasonable for gases as it has a relatively low viscosity.
Usually,
For such a small factor, the decision to neglect it was justified. Applying the correction would decrease the estimated heat transfer coefficient, which should not be a problem as the area required for heat exchange is well taken care of. It would also give a slight increase in the estimate.
4.11.4 OXYGEN STREAM PRE-HEATER.
4.11.4.1 FLUID ALLOCATION
Placing the higher temperature stream on the tube side will reduce the overall cost of design. Therefore, the saturated stream is placed in the tubes.
4.11.4.2 DUTY OF PRE HEATER
Let us assume that the amount of saturated stream used for pre-heating of the O2 stream gives off ‘ONLY’ its Latent Heat to the O2 – stream
Q= 877.04 ×103 KJ/hr
= 243.622 ×103 W
MASS OF SATURATED STREAM REQUIRED.
mS = 0.1414 Kg/sec
MEAN TEMPERATURE DIFFERENCE (ΔTm)
ΔTm= 0.986(114.823 0c)
= 133.215 0c
4.11.4.3 ESTIMATION OF U (Overall Coefficient)
An estimation of 200W/m2C for the overall Heat Transfer Coefficient is chosen as suggested by literature.
4.11.4.4 PROVISIONAL AREA.
A = 10.76m2
4.11.4.5 TUBE DIMENSION SELECTION
- Outer Diameter – 20mm
- Inner Diameter – 16mm
- Length of Tube – 6.10m
- Tube Effective Length- 6.0m
Small diameter tubes are chosen because they give more compact & cheaper exchangers. Use of longer tubes will reduce shell diameter thus lowering cost exchanger.
Heat Transfer Area of 1 tube = πdoL
= π(20/1000)(6)
= 0.37699m2
4.11.4.6 NUMBER OF TUBES REQUIRED
Number of tubes = 28.542
=28 tubes
4.11.4.7 TUBE ARRANGEMENT SELECTION.
A Triangular Tube Arrangement pattern is chosen as it gives higher heat transfer rates as compared to others. The recommended tube pitch is 1.25 times the Tube Outside Diameter(do). Tube Bundle Diameter is therefore
= 170mm
4.11.4.8 SHELL DIAMETER DETERMINATION
Using a Split Ring Floating Head unit, the Diameter clearance between the Shell and Tube Bundle is 50mm
Therefore,
Shell Diameter = 170 +50 = 220mm
4.11.4.9 TUBE SIDE COEFFICIENT
A Horizontal Condenser with condensation in the tubes is the usual arrangement for pre-heaters &vaporizers using condensing steam as the heating medium. It is customary to design purposes. For air- free steam, a coefficient of 8000W/m2 is used. Therefore,
hI= 8000W/m2
4.11.4.10 MASS VELOCITY IN SHELL (GS)
GS = 134.917Kg/m2s
4.11.4.11 LINEAR VELOCITY (Us)
US = 3.20m/sec
4.11.4.12 SHELL SIDE EQUIVALENT DIAMETER
For a Triangular pitch Arrangement
de = 1.10/do[pt2– 0.917do2]
= 14.2mm
4.11.4.13 AVERAGE PHYSICAL PROPERTIES OF SHELL FLUID
- Viscosity (µ) = 2.61 ×10-5 Pas
- Thermal Conductivity (K) = 3.448 × 10-2 W/mK
- Heat Capacity (Cp) = 0.9818 ×103 J/Kg 0C
4.11.4.14 REYNOLD’s NUMBER ON SHELL SIDE
Re = 73402.99987
4.11.4.15 PRANDTL’s NUMBER ON SHELL SIDE
Pr = 0.74318
4.11.4.16 HEAT TRANSFER COEFFICIENT (SHELL SIDE)
hs = 317.324W/m2 0c
4.11.4.17 OVERALL COEFFICIENT
U= 322.691 W/m2 0c
4.11.4.18 PRESSURE DROP CALCULATIONS
On the Shell Side
Re= 73402.99987
JF= 3.6 × 10-2
ΔPs = 4(3.6×10-2)(220/14.2)(6000/220)(42.07×3.202)
= 26.2112 KN/m2 which is very acceptable
On the Tube Side:
The pressure drop on the condensing side or tube side is difficult to predict as 2 phases are present & the vapour mass velocity is changing throughout the tube side.
4.11.5 AIR-COOLED EXCHANGERS
Air-cooled exchangers should be considered when cooling water is in short supply or expensive. They can also be competitive with water-cooled units even when water is plentiful. Frank (1978) suggests that in moderate climates air-cooling will usually be the best choice for minimum process temperatures above 65°C, and water-cooling for minimum process temperatures below 50°C. Between these temperatures a detailed economic analysis would be necessary to decide the best coolant. Air-cooled exchangers are used for cooling and condensing. Air-cooled exchangers consist of banks of finned tubes over which air is blown or drawn by fans mounted below or above the tubes (forced or induced draft). Typical units are shown in Figure 2 below. Air-cooled exchangers are packaged units, and would normally be selected and specified in consultation with the manufacturers. The equation for finned tubes given below can be used to make an approximate estimate of the area required for a given duty (Sinnott, 2005).
FIGURE 4.7 AIR-COOLED EXCHANGERS
4.11.5.1 FINNED TUBES
Fins are used to increase the effective surface area of heat-exchanger tubing. Many different types of fin have been developed, but the plain transverse fin shown in Figure 2 is the most commonly used type for process heat exchangers.
FIGURE 4.8: FINNED TUBE
Finned tubes are used when the heat-transfer coefficient on the outside of the tube is appreciably lower than that on the inside; as in heat transfer from a liquid to a gas, such as in air-cooled heat exchangers.
The fin surface area will not be as effective as the bare tube surface, as the heat has to be conducted along the fin. This is allowed for in design by the use of a fin effectiveness, or fin efficiency, factor.
(Sinnott, 2005)
(4.11.1)
LMTD = 47.28°C
(4.11.2)
Prandtl Number
(4.11.3)
Thus, the Prandtl number for air at 216.4 °C = 0.69
Heat Duty Required
(4.11.4)
Hence, the heat duty Q of the exchanger = 1.013 KJ/kg °C
Overall Heat Transfer Coefficient for the Design
(4.11.5)
Trials with various values of U
TABLE 4.16: HEAT TRANSFER COEFFICIENTS WITH CORRESPONDING AREA AND FACE VELOCITY VALUES
S/N | U (KJ/hr m2°C) | A (m2) | vair (m/s) |
1 | 6.127 × 104 | 965.56 | 3.00 |
2 | 8.169 × 104 | 724.167 | 4.00 |
3 | 1.225 × 105 | 482 | 6.00 |
In addition,
(4.11.7)
Aface = face area (m2)
TABLE 4.17: CORRESPONDING FACE AREA AND FACE VELOCITY VALUES
vface (m/s) | Aface (m2) |
3 | 1135.96 |
4 | 851.97 |
6 | 567.91 |
Substituting Wair in (4.11.7) into (4.11.4),
(4.11.8)
ρair = density of air, 1.1762 kg/m3
So far, for heat exchanger parameters,
U = 1.2254 × 105 KJ/hr m2 °C
A = 482.78 m2
vface = 6 m/s
Aface = 567.91 m2
4.11.5.2 FAN COVERAGE
= 293.96 m2
For the design also, we choose to use two fans rather than one, as this takes care of cooling over a bit of a longer distance of fan stages, and provides insurance in case of failure of one fan or the other.
4.11.5.3 FAN DIAMETER
With the two identical fans to be used the diameter is simply computed with the diameter, thus;
Diameter of fan = 13.45 m
General Properties of the Fans to be used as per industrial standards
Fan speeds vfan = 70 m/s
V-belt drive of about 30 horsepower
Forced draft fan system will be used as it uses less power in blowing cool air volume
4.11.5.4 FIN AREA AND TUBE AREA ANALYSES
(4.11.10)
(4.11.11)
(4.11.12)
Dfin = Diameter of fin = 12.7 mm
De = External diameter of the tube = 41.2 mm
Di = Internal diameter of the tube = 37.2 mm
W = Width of tube = 4.00 m
Lfin = Length of fin = 68.2 mm
L = Length of tube = 15 m
AHT = Total heat transfer area per length of tube = 0.01644 m2/m
Number of tubes per row of each metre in a tube bank = n× =
With the chosen pitch, P = 47.625 mm; n× = 20.997 ≈ 21 tubes per row
Number of rows n, chosen = 4; and given that W = 4.00 m,
Total number of tubes, N = n× × W × n = 336 tubes.
Because liquids are incompressible, Equation 1 may be used to calculate the work required to pump a liquid. The kinetic energy term is small compared to the other terms and is neglected. Therefore, Equation 4.11.1 reduces to
g∆z + ∆p/ρ+ W+ E = 0, defining points 1 and 2,we have,
g (z2 – z1,) + (p2 – p1,)/ρ + W + E = 0 (4.12.1)
The friction pressure loss term is split into two parts, one for the suction side of the pump, Es, and, the other for the discharge side of the pump, ED. Thus, Equation 1 becomes, after solving for W.
W = g (z1 – z2) + (p1 – p2)/ρ – (Es + ED) (4.12.2)
Frequently, we must make a preliminary estimate of the pump work. Manufacturers do not stock all pumps and other expensive machinery because of the cost of carrying an inventory. The machinery is manufactured on receipt of an order from a customer. Manufacturing some process machinery, may take six months or longer. To save time in implementing a project will require ordering equipment having long delivery times before completing a detailed design. Also, the management of a firm will require an estimate of the cost of a project to prepare a budget or a proposal for a customer. Once the work is estimated, the pump shaft power,
Pp = mW/ ɳP (4.12.3)
where, ɳp – the pump efficiency, includes both the hydraulic and mechanical frictional losses. Below outlines a calculation procedure for calculating an approximate pump size.
4.12.1 Approximate Pump-Sizing Calculation Procedure
1. Define the flow system, i.e., locate points 1 and 2. The pressures p1 and p2 will be known at these points.
2. Locate the process equipment according to the rules-of-thumb which is zero above ground level for pumps.
3. Estimate z 1 and z2.
4. Estimate the frictional pressure losses Es and ED according to the table 2 given below.
5. Calculate the pump work from Equation (4.12.2)
6. Calculate the pump shaft horsepower using Equation (4.12.3) and the pump efficiencies
given in the excel spreadsheet.
7. Calculate the electric-motor horsepower using the motor efficiency given in
the spreadsheet.
8. Select a standard electric-motor horsepower using the spread sheet to obtain approximately
a 10% safety factor.
TABLE 4.18: APPROXIMATE FRICTIONAL PRESSURE DROP ACCROSS PROCESS EQUIPMENT
4.12.2 THE METERING RAM PUMP
The pumped fluid contacts only the inside surface of the tubing. There are no other valves, O-rings, seals or packing to worry about in a peristaltic pump. Therefore, the only compatibility to worry about in a peristaltic pump is the tubes for the fluid being pumped. Of all the design parameters, the compatibility is the first one that need to be considered.
The tube is made elastomeric in order to maintain the circular cross section of cycles of squeezing in the pump. This requirement eliminates a variety of non-elastomeric polymers that have compatibility with a wide range of chemicals, such as PTFE, polyolefins, PVDF etc. from consideration as material for pump tubing. Elastomers, both natural and synthetic, have common characteristics including elastic recovery after stress, flexibility, extrusion resistance, and relative impermeability to gases and liquids. Each class of elastomer has its own unique properties and performance that can be modified by the inclusion of other ingredients.
Reasons why tube is made elastomeric and not plastic are because elastomer provide :
1. Very good dimensional stability over a broad temperature range
2. High compression set resistance
3. Excellent extrusion resistance at high temperatures and pressures
4. Retention of sealing force during pressure and temperature cycling (a major problem with many plastics)
5. Elastomers are long-chain polymers connected by cross-links that impart strength, resilience and elasticity, and these cross-links are very stable to heat and high pressure. Plastics are also long-chain polymers, but they are not connected by chemical cross-links. Plastics acquire their strength when the chains orient with one another and become crystalline in regions. These regions may deform or melt under high pressure and temperature.
There are over 20 classes of elastomers. Of all these classes, the most ideal elastomer for this work is EPDM (ethylene propylene diene Monomer) + polypropylene (as in Santoprene).
Reasons why EPDM (ethylene propylene diene Monomer) + polypropylene (as in Santoprene) is the most ideal :
1. It has a wide service temperature range
2. EPM elastomers have excellent resistance to ozone, water and steam, alkalis and acids, salt solutions and oxygenated solvents
3. Very good balance of compression set, flex resistance, physical strength, low temperature flexibility, weather resistance properties, and resistance to acid condensates
4. Outstanding resistance to high heat; excellent resistance to oil, gasoline, hydraulic fluids and hydrocarbon solvents; very good impermeability to gases and vapor; very good resistance to weather, oxygen, ozone, and sunlight; good flame retardant.
5. EPDM + polypropylene have the best fatigue resistance compare to other elastomers
4.12.2.1 OCCLUSION
The minimum gap between the roller and the housing determines the maximum squeeze applied on the tubing. The amount of squeeze applied to the tubing affects pumping performance and the tube life – more squeezing decreases the tubing life dramatically, while less squeezing decreases the pumping efficiency, especially in high pressure pumping. Therefore, this amount of squeeze becomes an important design parameter.
The term “occlusion” is used to measure the amount of squeeze. It is either expressed as a percentage of twice the wall thickness, or as an absolute amount of the wall that is squeezed.
Mathematically;
Where;
For this design work , the wall thickness of the tube of the peristaltic pump(t) is 4mm and the minimum gap between the roller and the housing(g) is 1.6mm so the percentage occlusion is calculated using the above formular
Occlusion is one of the key peristaltic pump design parameter because it affects not only the efficiency of the fluid movement in the pump but the life span of the tube. The higher the occlusion, the more efficiently the pump moves fluid and the lower the occlusion, the less efficiently the pump moves fluid. The occlusion not only alters the efficiency of the pump but also the lifespan of the tubing. By increasing the occlusion, you are squeezing the tubing with greater force, which will wear out the tubing material faster. Prepare replacement tubing are provided because of the high occlusion , and because a replacement tubing may be needed is one of the reasons why EPM elastomer tubing is the choice of tubing because it is inexpensive.
5 MECHANICAL DESIGN
5.1.1 DESIGN PRESSURE
5.1.2 DESIGN TEMPERATURE
5.1.3 MATERIAL OF CONSTRUCTION
The wall of the gasifier is made of Austenitic stainless steel (Type 316) as in the storage tanks.
Lining Material (Refractory block):Refractory liners are used on the working face of entrained-flow slagging gasifiers that react coal, petroleum coke, heavy fuel oil or other feedstock with oxygen and water. The refractory liners protect the gasifier shell from elevated temperatures, corrosive slags, and thermal cycling during gasification. Refractory failure is primarily by two means which are corrosive dissolution and spalling. High chrome gasifier materials have evolved as the material of choice to line the hot face of gasifiers, yet the performance of these materials does need to improve by coating it with substances like magnesium oxide, aluminium oxide and/or chromium oxide (Bennet, 2004).
Therefore,
The refractory liner for the heavy fuel oil gasifier is: Chromium oxide coated with zirconium oxide and aluminium oxide (Cr2O3: 90%, Al2O3: 3%, ZrO2: 7% in weight %)
5.1.4 THICKNESS OF THE REFRACTORY BRICK
Assuming that the ratio of the thickness of the vessel to the lining material is taken as 8:1, the thickness of the refractory lining is therefore = 90.6/8 mm = 11.325 mm
5.1.5 MINIMUM WALL THICKNESS
The minimum thickness required to resist the internal temperature of the gasifier is calculated thus,
5.1.6 MINIMUM HEAD THICKNESS
An Ellipsoidal head is chosen as the closure for this vessel because it is relatively cheaper than the torispherical head and it can withstand the design pressure of the vessel (Coulson and Richardson, 1999). The minimum thickness required is obtained thus,
Thickness of the head = 92.2 mm
5.1.7 VESSEL SUPPORT
Skirt Support is chosen because it is suitable for tall and vertical columns as it does not impose concentrated load on the vessel.
With the heat exchanger geometry defined, the mechanical design calculations must be done to ensure that the heat exchanger design is valid for the design pressure and conditions. The typical calculations are:
- Calculation of shell wall thickness.
- Calculation of nozzle wall thickness.
- Calculation of tube plate thickness.
SHELL WALL THICKNESS DETERMINATION
Pi= 3000 kPa
Di = 1.078 m
At the shell side mean temperature of 192oC,
f = 134 × 106N/m2
Therefore,
e = 3000000( 1.078)/ [2(134 × 106) – 3000000]
= 12.2 mm
Other design specifications include:
- Design Pressure = 110% of operating Pressure = 3300 kPa
- Design temperature = Maximum shell temperature = 220oC
- Corrosion Allowance = 4 mm
5.3.1 MATERIALS FOR CONSTRUCTION:
Carbon Steel is advised because, of its operability at not so high-pressure, because of its hardness and malleability and because it is most popular and therefore easy to obtain.
5.3.2 PACKING:
Interlox saddle packing was chosen because they are more efficient due to greater surface and improved hydrodynamics. They are made with a variety of holes and protrusions to enlarge the specific surface area. Because of their open structure and large specific surface area, mass transfer efficiency is high when proper distribution of liquid and gas over the cross section can be maintained. It also important to note that when ceramic construction of packing is suitable, saddles are the preferred packing.
5.3.3 DESIGN PRESSURE
Assuming 8% above operating pressure
= 1.08 x 4241.325 KN/m2
= 4580 .631 KN/m2
(4580.631-101.325) gauge
= 4479.306 kN/m2 gauge
5.3.4 DESIGN TEMPERATURE
This is obtained as,
= Highest Temperature + allowance for uncertainty
Assuming an uncertainty of 80oC
Therefore, design temperature= (250+ 80) oC
=330oC
5.3.5 TENSILE STRENGTH
At 25oC, the tensile strength of Carbon =210N/mm2
At 500oC, the tensile strength of Carbon is 450 N/mm2
At 330oC, the tensile strength of Carbon will be,
TABLE 5.1: TENSILE STRENGTH VALUES AT DIFFERENT TEMPERATURES
TEMPERATURE, OC | TENSILE STRENGTH, N/MM2 |
25 | 210 |
330 | X |
500 | 450 |
Interpolating we have,
(330 – 25) / (500 – 25) = (x – 200) / (450 – 210)
x=154+200
= 354N/mm2
5.3.6 DESIGN STRESS:
At 300oC, the design strength of Carbon = 85N/mm2
At 350oC, the design strength of Carbon is 80 N/mm2
At 330oC, the design strength of Carbon will be,
(COULSON AND RICHARDSON, VOL 6)
TABLE 5.2: DESIGN STRESS VALUES AT DIFFERENT TEMPERATURES
TEMPERATURE, OC | DESIGN STRESS, N/MM2 |
25 | 85 |
330 | X |
500 | 80 |
Interpolating we have,
(330 – 300) / (350 – 300) = (x – 85) / (80 – 85)
X = τ = 82 N/mm2
Nominal design stress = 1.5 × = 1.5 x 82
= 123 N/mm2
5.3.7 CHOICE OF CLOSURE
Minimum wall thickness required for a cylindrical shell
e= Pi Di / 2f – Pi
Given that,
Pi = 4241.325 KN/m2
Di = Internal diameter = 0.5275 m
therefore,
E = (4241.325 × 0.5275)
2 × 82000 – 4241.325
= 14 mm
Corrosion allowance = 2 mm
Minimum thickness of wall required = 14 mm + 2 mm = 16 mm
Choice of closure = Hemispherical head
Optimum thickness ratio for a hemispherical head to the thickness of the vessel = 0.6 (Coulson and Richardson, 2005)
Thickness of the hemispherical head = 16 x 0.6 mm = 9.6 mm
Type of Vessel Support = Skirt Support
5.4.1 Shell Thickness
Thickness of shell,
where,
Inner diameter of vessel (D) = 1.3 m
Working pressure = 1.013 ×106 N/m2
Design pressure (P) = 1.1× 1.013 x 106 N/m2
Permissible Stress (f) = 115 × 106 N/m2
Joint Efficiency (J) = 0.85
Corrosion allowance (c) = 2mm
hence,
So outer diameter of shell
- Axial Stress Due to Pressure
Axial stress due to pressure,
- Stress due to Dead Load
- Compressive Stress due to weight of shell up to a distance X
- Compressive stress due to weight of insulation at height X
Insulator used is asbestos
Thickness of insulation, = 100mm
Diameter of insulation,
Density of insulation = 575 kg/m3
Mean diameter of vessel =
For large diameter column,
- Compressive stress due to liquid in column up to height X
- Effect of attachments
- Packing weight
- Head weight
- Ladder
Density of packing (Plastic pall rings) = 53 kg/m3
Packing weight =
= 690.11 X N
Head weight (approximately) = 35000 N
Weight of ladder = 1600 X N
5.4.2 SUPPORT FOR ABSORBER
Material used is structural steel (IS 800)
Skirt support is used
Inner diameter of the vessel = Di = 4.69m
Outer diameter of the vessel = Do = 4.70m
Height of the vessel = H = 10.054m
Density of carbon steel = = 7700kg/m3
Density of packing = = 53 kg/m3
The catalytic converter primarily functions to provide surface area required for the exothermic reaction involved in the water-gas shift reaction and also to house the catalyst required for the reaction. The materials that make entry into the converter include steam and flue gases which exit the initial H2S removal stage and basically include hydrogen, carbon monoxide. Hydrogen sulphide, methane and nitrogen. The major aspects that will be considered in the mechanical design include:
- Operating and design temperatures and pressures
- Vessel dimensions and orientation
- Construction materials
- Type of vessel heads
5.5.1 Operating and Design temperatures and pressures
The operating temperature of the catalytic converter: 380 0C
The operating pressure of the catalytic converter: 1200 kPa
The design temperature of the catalytic converter: 480 0C (catalyst)
The design pressure of the catalytic converter: 1.1 1200 kPa = 1320 kPa
The maximum operating with respect to catalyst degeneration: 476.67 0C
5.5.2 Vessel Dimensions and Orientation
The major dimensions have earlier been calculated in the chemical engineering design section of this unit; the diameter being 3.518m and total height of 23.41m. Minimum wall thickness – the thickness required to ensure that any vessel is sufficiently rigid to withstand its own weight, and any incidental loads; and for a diameter of about 3.5 m, this thickness is about 16 mm. Also, a 3mm corrosion allowance is added. The “corrosion allowance” is the additional thickness of metal added to allow for material lost by corrosion and erosion, or scaling.
5.5.3 Construction Materials
Construction materials for pressure vessels are usually plain carbon steels; low and high alloy steels, other alloys, clad plate, and reinforced plastics. Because the temperature of the reactor shell is very high, the reactors must be made of alloy steel which can sustain high temperature and is highly resistant to hydrogen corrosion. A “cold wall” reactor is lined with heat-insulating material. The temperature of the reactor shell is quite low, ordinary low alloy steel can be used for making such reactors.
Alloy steels contain one or more alloying agents to improve mechanical and corrosion-resistant properties over those of carbon steel.
Nickel increases toughness and improves low-temperature properties and corrosion resistance. Chromium and Silicon improve hardness, abrasion resistance, corrosion resistance, and resistance to oxidation.
Molybdenum provides strength at elevated temperatures.
5.5.4 TYPE OF VESSEL HEAD
The vessel head indicates the closure. Ellipsoidal heads will be made use of. The ellipsoidal head thickness can be calculated using the following formula:
where, Pi – is the internal pressure; = 1200 kPa =1.2 Nmm-2
Di – the internal diameter; = 3.518 m
J – the joint factor; which is equal to 1 as a result of the absence of joints
f– the design stress at the specified temperature, equal to 180 N/mm2
Others include:
5.5.5 Openings required
Two openings are required:
An entry opening at the vessel top
An exit opening at the vessel bottom
Removable baffles for catalyst loading and discharge
5.5.6 Heating and Cooling Jackets or Coils.
Since its been established that a cold wall reactor will be used for the wall of the catalytic converter, implying an adiabatic arrangement to be ensured by incorporating on the reactor body an insulating material.
5.5.7 Internal fittings specification
The reactor will also consist of a reactor cylindrical shell, inlet diffuser, vapor-liquid distributor, scale removing basket, catalyst supporting plate, catalyst pipe, quench hydrogen box and a re-distributor, outlet accumulator, catalyst removal port and quench hydrogen pipe.
Also needed are Skirt supports of about 5 mm thickness;
FIGURE 5.1 SKIRT-SUPPORT
Base rings and anchor bolts for the supports.
FIGURE 5.2 DOUBLE PLATE WITH GUSSET
Design stress 240N/mm2
Construction material ; low alloy steel
Tray thickness; 12mm
Design temperature; 30 – 45oC
5.6.1 Design pressure:
This should be 10% greater than operating pressure
=
5.6.2 Wall thickness
e =
e = wall thickness
Pi= internal design pressure
Di= internal chamber
= design stress
e =
= 12.9 mm
Using corrosion allowance of 2mm
e= 14.9mm
5.6.3 Support
Skirttype is recommended
Material for the absorber shell is Carbon steel
5.7.1 Shell Thickness
Thickness of shell,
where,
Inner diameter of vessel (D) = 1.3 m
Working pressure = 1.013 ×106 N/m2
Design pressure (P) = 1.1× 1.013 x 106 N/m2
Permissible Stress (f) = 115 × 106 N/m2
Joint Efficiency (J) = 0.85
Corrosion allowance (c) = 2mm
Hence,
So outer diameter of shell
5.7.2 Axial Stress Due to Pressure
Axial stress due to pressure ,
5.7.3 Stress due to Dead Load
5.7.3.1 Compressive Stress due to weight of shell up to a distance X
5.7.3.2 Compressive stress due to weight of insulation at height X
Insulator used is asbestos
Thickness of insulation, = 100mm
Diameter of insulation,
Density of insulation = 575 kg/m3
Mean diameter of vessel =
For large diameter column,
5.7.3.3 Compressive stress due to liquid in column up to height X
5.7.4 Effect of attachments
- Packing weight
- Head weight
- Ladder
Density of packing (Plastic pall rings) = 53 kg/m3
Packing weight =
= 690.11 X N
Head weight (approximately) = 35000 N
Weight of ladder = 1600 X N
5.7.5 SUPPORT FOR ABSORBER
Material used is structural steel (IS 800)
Skirt support is used
Inner diameter of the vessel = Di = 4.69m
Outer diameter of the vessel = Do = 4.70m
Height of the vessel = H = 10.054m
Density of carbon steel = = 7700kg/m3
Density of packing = = 53 kg/m3
With the heat exchanger geometry defined, the mechanical design calculations must be done to ensure that the heat exchanger design is valid for the design pressure and conditions. The typical calculations are:
- Calculation of shell wall thickness.
- Calculation of nozzle wall thickness.
- Calculation of inner tube wall thickness.
- Calculation of expansion joint dimensions (to compensate for shell and tube side differential expansion due to temperatures differences.
- Calculation of tube plate thickness.
5.8.1 FIRST EXCHANGER
5.8.1.1 Shell Wall Thickness (Corrosion Allowance = 2 mm):
(Sinott, 2005)
Where f is the design stress, and Pi is the internal pressure.
Design pressure; take as 10 per cent above operating pressure,
= 31.9 bar
= 3.19 N/mm2
Typical design stress f = 540 N/mm2
e = = 1.70; with J = 0.85 for shell and tube exchangers
Adding corrosion allowance, 1.70 + 2 = 3.70, say 4.00 mm
5.8.1.2 Nozzle wall thickness:
Tube has been designed to provide entrance for nozzle = (0.2 shell diameter)
Thus nozzle diameter =
Nominal thickness at this condition is 0.5 in (=12.7mm) (Shilling et al., 1997)
5.8.1.3 Inner tube wall thickness:
With the tube dimensions selected according to standard,
Thickness =
5.8.1.4 Calculation of tube plate thickness:
The minimum plate thickness enough to withstand the bending and shearing force is gotten from literature as:
Minimum plate thickness = 0.75
5.8.1.5 OTHER SPECIFICATIONS
Number of baffles Hence
Baffle clearances
The edge distance between the outer-tube limit (OTL) and the baffle diameter has to be sufficient to prevent tube breakthrough due to vibration.
Baffle clearance = 11mm (for shell ID m) (Shilling et al., 1997)
Distance from tube O.D to centre of partition
Distance = 9.5mm (for ID)
Design temperature
Built to withstand 10% above highest stream temperature = (373.4 °C) × 1.1 ≈ 411 °C
Design pressure
Take as 10% above operating pressure = (30-1) × 1.1 = 39.1 bars
SECOND EXCHANGER
Shell wall thickness e (Corrosion Allowance = 2 mm):
(Sinott, 2005)
Design pressure; take as 10 per cent above operating pressure,
= 26.4 bar
= 2.64 N/mm2
Typical design stress f = 540 N/mm2
e = = 3.07; recall J = 0.85
Adding corrosion allowance, 3.07 + 2 = 5.07, say 6.00 mm
Nozzle wall thickness:
Tube has been designed to provide entrance for nozzle = (0.2 shell diameter)
Thus nozzle diameter=
Nominal thickness at this condition is 0.432in (=10.97mm)
Inner tube wall thickness:
Thickness=
Calculation of tube plate thickness:
Minimum plate thickness=0.75
OTHER SPECIFICATIONS
Number of baffles Hence
Baffle clearances
Baffle clearance=13mm (for shell IDm) (Shilling et al., 1997)
Distance from tube O.D to centre of partition
Distance = 9.5mm (for IDm)
Design temperature
Built to withstand 10% above highest stream temperature = (380.9 °C) × 1.1 ≈ 420 °C
Design pressure
Take as 10% above operating pressure = (25-1) × 1.1 = 26.4 bars
FIGURE 5.3: PHYSICAL LAYOUT OF A 2-TUBE PASS SHELL AND TUBE EXCHANGER
CHAPTER SIX
6 PLANT HAZARD AND OPERABILITY STUDY
GASIFIER INTENTION: to cause partial oxidation of the heavy oil feedstock.
TABLE 6.1:HAZOP ANALYSIS FOR GASIFIER
GUIDE WORD | DEVIATION | CAUSES | CONSEQUENCES | ACTION |
NO | Flow (steam & gas) | Control valve stuck closed | Delays the reaction | Fit low temperature alarm |
MORE | Flow (Steam/Oxygen) | Failure of ratio flow or failure of control valve |
|
1)Alarms
2) Automatic shutdown |
AS WELL AS | Composition | Refractory particles from reactor | Possible blockage of boiler tubes | Install filters up-stream of boiler |
TABLE 6.2: HAZOP ANALYSIS FOR WASTE HEAT BOILER
GUIDE WORD | DEVIATION | CAUSES | CONSEQUENCES | ACTION |
NONE | No tube side fluid flow | Failure of inlet tube side valve to open | Process fluid temperature is not heated accordingly | Install Temperature indicator before and after the process fluid line
Install TAH |
MORE | More tube side fluid flow | Failure of inlet tube side valve to close | Output of Process fluid temperature too high | Install Temperature indicator before and after process fluid line
Install TAL |